Our new timelapse is out!

We’ve come a long way since August 2012 when excavation first began, and now our facility is really starting to take shape! Here’s the latest:

  • 80+ feet above ground.
  • Nearly 20,000 cubic metres of concrete poured to date preparing for 5 levels of development.
  • 4 cranes onsite contributing to the installation of the structural steel that will sustain the upper levels.
  • 4th and largest crane is in the process of installing the last of 5 girders, for a total of 750 tonnes of steel in place. This represents 50% of the total tonnage of steel for this project!

For the full picture, check out the latest construction progress in our newly released timelapse video!